The INTECO Company, Zagreb presented today, in front of distinguished representatives from the world of business, the first robot for hydrodynamic treatment of concrete and metal surfaces developed in Croatia.  http://youtu.be/LMf7iZrSaE8

14.09.2011

It is our great pleasure that we can inform you that after five years of intensive development, we have successfully completed our first commercial robot for hydrodynamic treatment of concrete and metal surfaces R Jet – 062...


In the beautiful landscape of Peruća Lake, we have started work on the repair of the decant structure of the Peruća hydroelectric dam. Job consists of repair of concrete and cracks on the wall of the decant structure and on the bottom of the intake. The procedure has been envisaged in a way that degraded...


On a residential building in Gračani, Zagreb, investigation is being performed with a purpose to detect problems linked to humidity and moisture, including water pouring and any other manifestation. After the investigation will be finished in the above-mentioned fields, an expert opinion will be given as a basis...


Waterproofing was required on a residential building K7 - near the lake Jarun in Zagreb. Specific requirements concerning the job are seen in the "strange" way the roof had been designed. It has stressed descents with no visible elements of roof drainage...


Concrete surface protection job is being done inside the zinc galvanization plant, owned by an Italian company based in Croatia ITALIKACINK Ltd. Work is being done to protect concrete from aggressive influence of acid, leach etc...


On the hydroelectric power plant Čakovec there is ongoing reparation of a reinforced concrete fixer for the hydraulic shutter of the dam area. Because of the requirement for swiftness in completion of the job, job is done from the dam bridge with a crane and a basket. Method used...


Work started on roof and facade sanation of the waterproof system on the building owned by Croatian Telecom - HT in Draškovićeva Street, Zagreb. It is a quite demanding job since there are lots of installations on the roof, including air conditioners and other...


Work has started on the waterproofing of the upper ceiling plate of the underground garage on a residential building - Project Heinzelova. Project owner is Splitska banka and the main contractor is FKT Ltd. - Ivanić-Grad. Waterproofing is being implemented with SIKA pvc film.

 